In short. Most problems on a building site happen between crews: the painters hand over the walls, the door installers scratch them, and nobody is to blame. We sign off every stage with a handover record, photos signed by the crew, and a third person present. Crews know the rules, penalties and bonuses in advance. Hidden works are photographed and filmed, and timber for stairs is dried for up to three weeks. Every villa in the complex is different, so the checks are individual too.
The tour of the Serenity site in Sanur is led by our partner and project manager Andrey, who has worked in 30 countries and built in Russia and Turkey.
Mistake 1. No handover between crews
The painters finish the walls, then the doors arrive. If the installers scratch a wall or damage a corner, who is responsible? "They can say: boss, it was already like that. Don't stress us, it's your problem," the project manager explains.
So we record every finished job: a handover record, photos, the crew's signatures and a third person who accepts it. Then there is nothing to argue about: the wall was perfect, so it was damaged when the doors went in.

Mistake 2. Crews don't know the rules
Before work starts, the project manager briefs each crew on the site rules: the consequences of mistakes and the bonuses for finishing on time. He then asks a long-serving site assistant to repeat it in his own words. "Our view of the world doesn't always match theirs," he says. A local assistant gets the message across faster.
With crews we have worked with for a long time there are almost no conflicts: they already know our standards.
Mistake 3. Hanging on to bad contractors
"If you hold on to people who put you in an awkward position because you think there's some benefit, that benefit is an illusion. You'll end up overpaying," the project manager says. Work with people who have a good reputation and portfolio, and do not hesitate to part with those whose reputation has slipped. That is how deadlines and budgets are kept.
Mistake 4. No photo record of hidden works
Much of a house ends up covered by walls, floors and ceilings. Afterwards it cannot be checked; you can only look at photos and video. "Many people don't just forget about this, they don't even know about it," the project manager notes. We photograph hidden works at every stage.
Mistake 5. Rushing the timber
Serenity's stair treads are teak. The wood must be dried, which takes up to three weeks. Fit it wet and the staircase will warp later. So the stairs are ordered early, without waiting for the wall to be ready.

Doors show the standard
Fitting the doors is the final stage, and it shows the quality of the whole house: nothing cut short, nothing left loose. When the result matches what the architect and designer intended, the project manager calls it "a dopamine hit that doesn't come cheap", the thing worth working for.
Every villa is different
"Every unit here is individual. It's not 98 villas of two or three types printed out like a row of garages," the project manager says. Each villa has its own window and door geometry, its own garden and its own privacy: you neither see nor hear the neighbours, without extra fences. It is harder to build this way, but guests later describe each villa in their own words.
Apartment 10 in the complex was ready for rent before construction finished: it has its own parking, so the site does not bother guests.
What he would show a hesitant investor
"I'd suggest living here for a week or two, maybe a month. After that they could decide based on their own experience," the project manager says. Not from pictures and stories, but from living in the house.

Read next: Hidden construction defects, Serenity from the inside.
Key points
- Sign off every construction stage with a record and photos.
- Crews should know the rules, penalties and bonuses in advance.
- Hidden works must be photographed: they cannot be checked later.
- The best way to check a villa is to live in it.
FAQ
How can I check the build quality of a villa?
Ask the developer how they sign off work from each crew, and whether there are handover records and a photo record of hidden works.
Why does timber need drying before fitting?
Wet timber moves after installation: stairs and floors warp.
Are the villas at Serenity identical?
No. Every villa and apartment in the complex has its own layout and character.